Cranleigh Leisure Centre Update – Construction Starts Early 2027

Cranleigh Leisure Centre – Pre-Construction Agreement Signed: An Update on the Timeline

In our previous article at the end of August we highlighted growing uncertainty around the Cranleigh Leisure Centre project. The Pre-Construction Services Agreement (PCSA) had not yet been signed, timelines continued to slip, and residents and businesses were left waiting for clearer information on parking, construction arrangements and overall progress.

We can now report a significant step forward. On 13 October 2026 Waverley Borough Council announced that it has signed the Pre-Construction Services Agreement (PCSA) with Willmott Dixon, the preferred contractor. This formal agreement begins the detailed planning phase in which design, costs and construction methods will be finalised before building work starts on site.

According to the Council, work on site is expected to begin in early 2027, with the new centre scheduled to open in autumn 2028. This matches the timeline that Councillor Liz Townsend had previously indicated would protect the important Christmas trading period on the High Street. The existing leisure centre will continue to operate under Everyone Active until the new facility is ready.

The PCSA phase is critical. It allows the Council and Willmott Dixon to refine the scheme whilst aiming to protect the quality and sustainability of the finished building. External cost consultants AtkinsRéalis have independently reviewed proposed changes. The new centre remains planned as a Passivhaus facility featuring a six-lane 25-metre pool, teaching pool with movable floor, large gym, multi-purpose studios, café and improved accessibility features.

Parking during construction remains a major local concern. Willmott Dixon has committed to providing a minimum of 100 spaces in the Village Way car park throughout the works. The Council states it will continue working with the contractor to increase this number where possible. Council data suggests the two main public car parks currently operate at around 50% average capacity, though demand is higher on market days and Saturday mornings. Cranleigh Society has been conducting its own surveys and will continue monitoring once the Construction Transport Management Plan is published. That plan, required by planning conditions, will set out HGV routes and hours, storage, traffic management and final parking arrangements.

The Council recognises that the construction period will be challenging and encourages residents who are able to walk or cycle into the village centre, to help ease pressure on remaining spaces. Cranleigh Society will keep a close watch on how these arrangements work in practice and will obtain regular updates as details are confirmed.

While the signing of the PCSA removes one major source of uncertainty, many practical questions remain. Residents and businesses still need clear information on the precise construction start date, the final parking provision, and how disruption will be minimised.

Further updates from Waverley can be found on the project page at waverley.gov.uk/clcnewbuild. If you have observations or concerns about parking, access or any other aspect of the scheme, please get in touch with us at membership@cranleighsociety.org. We will keep residents informed as the next stages unfold.