Cranleigh Leisure Centre – Uncertainty Grows as Timeline Slips Again.

Delays and Amendment – 30th August

Remember and Imagine – can you think back to 2023 – just three years ago? Well now we are imagining 2029 – when Cranleigh returns to a peaceful and prosperous time and benefits from a new Passivhaus Leisure Centre. We want to be positive but we are all concerned about the details.

Cranleigh Society has been paying close attention to the development of the Cranleigh Leisure Centre. Waverley Borough Council met on the 30th June and voted on an amendment asking to publish the Pre-Construction Services Agreement in 7 days from its signing rather than 30, it was ultimately not passed. Cllr Liz Townsend also confirmed the statement she’d made on the morning radio, that she’d requested a postponement of the project until early 2027 to protect the Christmas trading period.

The most recent update on the WBC website is 13 July and on 30 August we are none the wiser on the signing of the Pre-Construction Services Agreement, the portfolio holder expected this to be within two weeks of the council meeting. Delays can occur for good reasons but this has raised further uncertainty for residents over the future of the project. WBC ‘s consultant, Atkins, are confident that costs are not expected to increase as a result of the delay, but in the event that they do, an amended budget will have to be agreed by the new Unitary Authority. Can the public rely on Atkins’ assessment?

Freedom of Information

Due to this delay, the council was requested by us to provide information on the framework used to decide the contractor Willmott Dixon to build the leisure centre. The Council used the “Procure Partnership National Contractor Framework” – details found HERE. It has been confirmed that there was a mini-competition. (Meaning a few suppliers from the list of 10 were invited to submit a proposal and price. The exact number of bidders is not known. Companies already approved are included in the framework.

Willmott Dixon was chosen as the supplier, therefore we ask what qualifications do they have to realise this project’s vision? First, they claim themselves to be the “leading Passivhaus contractor“. Their portfolio of works includes dozens of Passivhaus schools and a Leisure Centre project built for Spelthorne Council HERE. Potentially a compelling reason to award the project to Willmott who have delivered this larger project costing £43.5m in 2024. Issues were reported over safety and faulty air conditioning after opening. This is outlined in these BBC articles HERE and HERE. The issues were quickly resolved. They are a family-owned company and their financial accounts indicate a very healthy financial position. Perhaps providing some hope for those fearing delays during the construction period? For further reading on this prior project and the Passivhaus benefits, this article HERE provides more detail.

Eclipse Leisure Centre Spelthorne – Image from Eclipse Leisure Centre  | Willmott Dixon

Leisure Centre Parking – What We Know

Before the project can start the Council must be presented with Willmott Dixon’s ‘Pre-construction agreement’ and the ‘Construction transportation management plan’ and all parking plans within it. The portfolio holder Councillor Liz Townsend explained that this is still being drawn up, considered and agreements will be in late Autumn.

Waverley Borough Council released an update on the 13th July stating that “We are aware that parking remains a key concern for local businesses and some residents. We have been analysing usage at Cranleigh’s car parks and exploring alternative options. Over the next month, we will meet with Cranleigh Business Improvement District (BID), the Chamber of Commerce, the Parish Council and local ward councillors to discuss the challenges and identify ways to reduce the impact. We will then work with our contractor to develop solutions and share this information with the wider community as soon as possible, so people can plan ahead and disruption is kept to a minimum.” Waverley Borough Council, HERE

Cranleigh Society continues to conduct our own car park surveys, counting the number of empty spaces at several different days and times. Across these summer months we have observed plenty of empty spaces every time we have checked except on Thursday mornings. However, this doesn’t take into account the likely increased usage of cars during the cooler and wetter months. Cranleigh Society plans to continue monitoring and compare this data against the proposed plans.

Construction Transportation Management Plan

To protect residents, the planning conditions state that before development of the leisure centre begins a Construction Transportation Management Plan (CTMP) must be submitted. This will cover arrangements such as Parking, HGV hours, storage and traffic management. From Waverley’s latest message this seems to be nearing completion (as they’re consulting with stakeholders) and should be expected around the time the Pre-Construction Services Agreement is announced.

Lets keep the pressure on Waverley to ensure that the uncertainty for residents and businesses is removed. Please get in touch with us about your concerns.

What can we do?

In short, for now there is little that can be done. Consultation has happened and the supplier has been selected. It is now in the hands of Waverley Borough Council Officers and the supplier to ensure all documents are in place to fulfil planning conditions before construction begins.

All the various planning conditions have to be met during the construction period, demolition phase and beyond its opening. Cranleigh Society is working to supply a full and summarised list of these conditions shortly which we can then monitor.

Join Cranleigh Society

As always, if you’re interested in what we do or wish to support us, please reach out to membership@cranleighsociey.org. Or, if you wish to join us visit this link for details on how to do so.

3 Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

  1. Do we know if the concerns expressed by the swimming club regarding the lack of spectator seats , has been addressed ? The club says they have been advised to hold galas at Haslemere pool but Haslemere say they already host Godalming so not possible . Club says club wont be sustainable for them with current plans. What facilities exactly will there be at the new centre ? Any idea ?