As you will be aware we have had major concerns about our ageing and deteriorating asbestos cement drinking water pipes for some time now. Due to the age of previous significant development in Cranleigh in the 60’s, we suspected that they may contain crocidolite (blue asbestos), in addition to chrysotile (white asbestos). Although Thames Water assured us that the pipes were constructed from white asbestos, our own research did not reflect this, and we have been pushing for testing to be carried out.

Over the past two weeks we were successful in getting Thames Water to send a section of drinking water pipe, being replaced in the Hitherwood area, for independent testing to confirm the presence of blue asbestos (crocidolite). This has now been confirmed.

The presence of crocidolite (blue asbestos) is not the result we were hoping for, but it is in line with the guidance given on the Health and Safety Executive’s (HSE) website under the Asbestos section.  HSE state that asbestos cement pipes made prior to 1969 are likely to contain crocidolite.

A further section of pipe from the Summerlands area has been tested and this has been shown to contain only white asbestos. We have asked also requested details from Thames Water of the percentage of blue to white asbestos, and to assess how much deterioration has taken place in the pipes. Furthermore, we have requested that a section of pipe be tested from the Park Mead area, although we have been told that this will not be carried out until there is a burst pipe there. We will be challenging Thames water on this.

Blue and white asbestos have very different risks associated with them, with the crocidolite being considered more hazardous. We should stress that the majority of evidenced high risks are associated with inhaling asbestos fibres, however, there does appear to be a growing evidence base worldwide that suggests that there is also a risk associated with ingested fibres.

Recently Australia and New Zealand have announced replacement programmes for their asbestos cement pipes, and in the USA they already test drinking water for asbestos fibres, and have set maximum guidelines, testing is NOT carried out in the UK.

We have been asking the authorities, including the Drinking Water Inspectorate (DWI) and the Health and Safety Executive (HSE), since September 2016 to assess the risk to Cranleigh residents from a high percentage of ageing and deteriorating asbestos cement drinking water pipes without success. Asbestos cement pipes have a 50-70 year design life and some of these in Cranleigh are approaching 70 years old. The issue also affects residents in Dunsfold, Ewhurst and Alfold, we have not looked into any of the other surrounding areas. In a recent planning application in Waverley for development in Alfold, once again the Society advised Waverley of the existence of blue asbestos in the drinking water network, once again we were ignored.

We have questioned the position of the DWI.  Whilst their blanket statement broadly states that there is no consistent evidence to suggest that asbestos is dangerous when ingested, we have studied their database of evidence and that of other qualified evidence available and we are of the opinion that the DWI, and the World Health Organisation (WHO), have based their studies in the main on chrysotile (white asbestos).  Furthermore, many of the reports back in the 1970s and 1980s were sponsored by the asbestos industry, and in particular by the Chrysotile Institute, and they should be treated with some caution, as well as being based mainly on the effects of chrysotile.

In January 2017, in discussion with HSE, Cranleigh Civic Society circulated our own Risk Assessment under the Health and Safety Act looking at data from contemporary research carried out over the last few years, some of it by highly respected organisations such as the American Journal of Toxicology and Environmental Health (a leading publication respected around the world).  Our increasing concerns surrounding crocidolite remain, because of its needle-like structure, it has the potential to penetrate membranes in the body more easily than the more curly fibres of white asbestos.

Our research is continuing, and we have received this from a contact in New Zealand.  It was put out by Radio New Zealand and is now on their website:

‘A $2.2 billion price tag has been put on the cost of replacing the country’s asbestos water supply pipelines.

 Drinking water delivered through functioning asbestos pipes isn’t risky, but airborne particles from broken pipes can be dangerous.

 Asbestos cement pipes were installed for local water supply networks from the 1950s to the 1970s, and manufacturers stopped producing them in the mid 1980’s. The pipes’ life expectancy is about 50 years so many will be due for replacement.

 Functioning pipes being used for water do not pose a threat to health. The World Health Organisation has said swallowing asbestos present in water does not present the same cancer risk as inhaling dry particles. However, asbestos pipes that are cut or broken when dry can pose a health risk if particles are released into the air.

 

The Water Services Association of Australia has estimated it could cost $AU8b ($NZ9b) to safely remove Australia’s roughly 40,000km of worn-out asbestos piping.

Water New Zealand estimated the total length of this country’s water supply pipelines at 36,436km, with the network valued at $8.7b. It estimated 9000km of those pipes were made of asbestos cement and that they would need to be replaced in the next 20 to 30 years.

With many of the pipes nearing the end of their useful life, Water New Zealand chief executive John Pfahlert said local councils would have to do careful planning to make the replacement affordable to ratepayers. There were a number of available options cheaper than digging them out, such as relining existing pipes or leaving decommissioned pipes in the ground and placing new pipes around them, he said. Wellington Water spokesperson Alex van Paassen said replacing asbestos cement pipes, as opposed to those made of other materials, did require safety precautions. However, he said, those precautions would not add a significant amount to the overall cost of replacement. Mr van Paassen said pipes in Wellington were prioritised for renewal based on how critical the need for repairs was, or how many households were served, and not on whether they were made of asbestos.

 “Wellington Water had a regular pipe renewal schedule for all types of pipes”, he said.’

We have continued to keep our MP Anne Milton informed of our research and she has now arranged a meeting on 24th July in Cranleigh to investigate this further. Thames Water, the DWI and other relevant parties have confirmed their attendance.  This is also following the petition sent to Anne Milton following our public meeting on 25th May. We are grateful to her for listening to our concerns and seizing this opportunity to seek answers.

Cranleigh Civic Society, in consultation with the Government’s Health and Safety Executive, prepared a full Risk Assessment on the network of asbestos cement pipes in Cranleigh and sent this to Waverley Borough Council on the 29th January.  Waverley ignored it.

We are aware that this subject will cause a high degree of concern in the village and we will of course keep you informed of any developments.

Poo Brook still not resolved

Poo Brook still not resolved

Adrian Clarke of Cranleigh Civic Society and Cranleigh Borough Councillor Liz Townsend were interviewed by Surrey Radio this week about the severe pollution problems in the brook that flows out of a culvert behind Marks and Spencer’s car park.  The brook problem is also featured on the front page of the current edition of the Surrey Advertiser (Friday 31 March 2017).

Residents have been complaining to Thames Water about raw sewage in the brook for 8 years, and in 2015 Cranleigh Civic Society took samples from the brook and got an independent laboratory to test them.  The report, which showed very high levels of e coli, was sent to the Environment Agency who investigated it and immediately put it onto their ‘UK Priority Hot Spot List’.

Cranleigh Civic Society also tried unsuccessfully to get Waverley Borough Council’s Environmental Health Department to help to get this serious pollution issue resolved.  We suspect that the reason why Waverley did not want to get involved is because it would jeopardise their hugely unpopular draft local plan.  In case you didn’t know this, Waverley wants to dump 44% of its new housing allocation into the Cranleigh area.  The same Waverley we all have to pay our very high Council Tax charges to.

Since the Environment Agency got involved, Thames Water has been carrying out tests, putting dyes in outflows and feeding cables with cameras from the culvert back towards the High Street, but with mixed results.  Thames Water claims to have discovered several ‘misconnections’ over the last year, but they have been very secretive about the number and locations of these.  Misconnections are where a house or a commercial property illegally connects its foul drainage to rainwater pipes either intentionally, or by mistake.

An engineer from Thames Water told us that, over the weekend of  1-2 April 2017, his team had identified eight commercial properties in the High Street that had misconnections; an amazing admission considering that Thames Water have had crews out investigating this problem now on several occasions over the last two years!

The cost of all these investigations so far is huge, the Thames Water engineer told us, and that, as it is unfair to burden their customers with this cost, Thames Water will be seeking to recover the cost from the commercial premises in the High Street.

We are hoping that Thames Water will now issue 21-day notices to the offending premises in the High Street to correct their problems.  If the businesses ignore the 21 day notice, they can face large penalties.

Why is all this a problem?  Children were seen last summer playing in the brook building a dam, and they often retrieve footballs from the brook when playing on the adjacent field, and people walk their dogs next to the brook (and dogs like to jump into water).  Also, the brook joins Cranleigh Waters, a stream that is already heavily polluted and which has caused fish stocks to die out in Bramley.

We will keep you informed of any updates on this story.

Death of the Grampian Condition

Death of the Grampian Condition

It won’t have gone unnoticed to residents that both Crest Nicholson on the Horsham Road and Cala Homes on Amlets Lane have started developing their sites.

Both these sites had Grampian style conditions.  This was meant to prevent the start of the development until off-site works were completed on the sewerage network, including the sewage treatment works on Elmbridge Road. However, we were recently advised by planning enforcement at Waverley that the Grampian Condition wording is too woolly to enforce and doesn’t specifically mention the words sewage “TREATMENT”,  so no work to the sewage works are apparently included – another nail in the coffin for Cranleigh.

To say that we felt let down by the lack of rigour exercised in the planners’ wording of the Grampian and the lack of ability by Waverley to enforce it, is an understatement!

There is no consideration being given to existing residents, who after all fund the borough council, in the scramble to achieve a housing number at all costs.  We don’t need to remind you, that you will have to bear the brunt of polluted rivers, congested roads, odour nuisance from the sewage works, an over burdened GP surgery, the list goes on.


As you might remember Cala Homes had applied for their Grampian condition to be removed, however, Waverley Borough Council, in a rare moment of what seemed common sense, refused their request. Surprisingly, this did not stop work on Cala’s show houses.

Amlets 8 Jan 2017

The bungalow on the Horsham Road, which was acquired by Crest Nicholson to provide an access road to the site, was demolished long before their Grampian Condition was even discharged (such as it was), and work was also immediately commenced on the green fields to build 149 houses.  Grampian, what Grampian?

It was also pointed out that Crest’s Grampian was a little more lax than that for Cala Homes, despite all the initial concerns Thames Water had about this site and the need for huge on-site sewage storage tanks. These worries seem to have been a mere flash in the pan!

Not long after the first Crest spade was in the ground, they were plotting to build 121 more houses in the pristine green fields adjacent to this site.

Crest describes Cranleigh on their website:

“Cranleigh is a pretty Surrey village where one can enjoy a relaxed pace of life yet benefit from daily conveniences aplenty on the doorstep, including a selection of shops, cafes and restaurants.”

Crest Nicholson demolish Bungalow Horsham Road

Sounds idyllic, and surprising how keen developers are to emphasise that we are a “village” in their marketing literature.


Despite the unsustainable location of Cranleigh, on a rural road network, with little public transport, a heavy reliance on the use of the private car, limited employment opportunities, water quality issues, a high percentage of asbestos cement drinking water pipes, an inadequate sewage treatment plant, and on green fields to boot,  none of this matters, as long as the houses are built.

The ONLY reason for these dwellings is because we have NO GREEN BELT protection, nothing else, and national planning policy will be twisted at the whim of the planners to suit their ultimate plan for this area, which is CRANLEIGH TOWN.

However, before you start thinking, how bad can that be, it will be bad!  We are the only community in Waverley without green belt protection AND any environmental designation.  Farnham at least has the protection of Thames Basin Special Protection Area.  So going forward, Cranleigh will be the dumping ground for any, and all, unmet housing in Waverley.  However, Waverley Borough Council seem to be the winners, they have a convenient area, in the corner of the borough, which will be a cash cow for council tax, and with only 5 councillors (Farnham has 18) representing this area, and two of those with a declared pecuniary interest in development, this really does seem like a marvellous arrangement.

There is the rather inconvenient truth of Cranleigh Waters, which is polluted and failing in terms of the Water Framework Directive, but that can be smoothed over, by applying pressure to an overworked and under resourced Environment Agency (EA) with the promise of funds for river restoration  and flood plain replacement projects.

There’s the problem of the rural roads and A281, but as Matthew Evans, Ex-Waverley Head Planner, said it really doesn’t matter if people are stuck in traffic.  Obviously air quality issues and quality of life, for residents in this part of the borough,  was not something that disturbed his sleep.

And then there’s the ageing asbestos cement drinking water pipes, which have an extremely inconvenient habit of bursting whenever water pressure increases, still, studies of health risks are inconclusive, so it appears Waverley don’t need to worry about that either.  Despite the fact that we can find no reports that include the age of pipes we have here, or our particularly agressive type of water.

It would be difficult to imagine what would ever be considered as a material constraint by Waverley planners against development in Cranleigh, perhaps the discovery of uranium in the high street?

And to add insult to injury, the EA are now actively looking for replacement flood plain for this area, as let’s face it, they don’t want to create too much flooding downstream for Bramley and Guildford, residents there might start to wonder why the hell all this building was allowed, or should we say encouraged, on the natural flood plain we DID have.

However, we still have something up our sleeve and that’s you!

Joined together, you are the most powerful force.  Stronger than Waverley and stronger than developers.

Working together in big enough numbers, people can, and will, make a difference.  We can fight for fairness, we can fight for our community, and we can fight for our environment.

JOIN US


“Never doubt that a small group of thoughtful, committed citizens can change the world; indeed, it’s the only thing that ever has.”

Margaret Mead


 

EA Object to KPI Application

EA Object to KPI Application

The Environment Agency (EA) have objected to the KPI (now in the name of A2Dominion Developments Ltd) on the grounds that there is not an acceptable Flood Risk Assessment (FRA) for the site.


You can read the full objection by clicking on the link below:

EA obj KPI 4 Jan 2017


The main summarised reasons outlined in the EA objection letter are that the Flood Risk Assessment does not demonstrate that the development will be safe from flood risk for its lifetime, and the potential impacts of climate change have not been satisfactorily taken into consideration.

The Cranleigh Society has maintained serious concerns about the flood risk on this site, which is part of Cranleigh’s rapidly diminshing natural flood plain.

We are extremely glad that the EA have carried out a thorough study of the FRA and echoed many of the points that we raised in our letter against this application:

“Flood Risk

Although there is a presumption in favour of sustainable development however NPPF para 14 states that even if the development plan is absent, silent or relevant policies are out of date, permission should not be granted where specific Framework policies indicate it should be restricted, this includes flooding.

We also object on the grounds that the assessment of flood risk informing the measures proposed by the FRA to avoid, manage and mitigate flood risk, are incomplete and have not been appropriately secured for the lifetime of the development.  There also does not appear to be provision for increased climate change allowances agreed by the Environment Agency and the Government, published in February 2016.  These now require applicants and developers to assess a range of climate range allowances from 25% to 70% above the 1% AEP as part of planning applications. As the application appears to have been submitted to Waverley in November 2016 the new allowances and ranges should be used.

Document 9.0 WATER RESOURCES AND FLOOD RISK point 9.28 fails to mention the significant flooding on Alfold Road in 2013/14 or the flooding on Elmbridge Road.  the Our own FRA review by RAB consultants (Bedford) acknowledges that the recent flooding of December 2013 on the Cranleigh Waters and Littlemead Brook has not been recognised within the flood risk assessment (FRA) dated October 2014.  They go on to say that the extreme nature of the flood in December 2013 warrants recognition within the FRA and an assessment of flood depths and extents at the site if possible.  Additionally, given the nature of flooding in December 2013 and the significant groundwater flooding experience across many parts of the Thames Catchment throughout winter 2014, it would be prudent to include this within the assessment of groundwater risk to the site.

Water Environment Ltd October 2016 appears to be missing Appendices B, C and D. Previously Appendix B of the FRA shows that EA “Product 4” flood data, received 29 July 2014, was used for the assessment.  The EA have updated their flood modelling in the area since this data was obtained. The data used in the FRA has therefore been superseded. Without incorporating all this data we do not believe an appropriate nor up-to-date assessment of flood risk has been undertaken.

Furthermore, evidence exists and data has been collated of the recorded flooding in the vicinity of this development during 2013/14.  This has been submitted in support of a planning application ref WA/2014/0912 by Berkeley Strategic Land Ltd in Appendix 1 from “Technical Review of Flood Risk Assessment (FRA) for the construction of 425 dwellings on land south of Cranleigh, Surrey” dated August 2014.  The FRA should take this evidence into account.

Paragraph 040 of the Planning Practice Guidance (PPG) states: “To demonstrate to the satisfaction of the local planning authority that the development will be safe for its lifetime taking account of the vulnerability of its users, a site-specific flood risk assessment may need to show that appropriate evacuation and flood response procedures are in place to manage the residual risk associated with an extreme flood event.  Proposals that are likely to increase the number of people living or working in areas of flood risk require particularly careful consideration, as they could increase the scale of any evacuation required. To mitigate this impact it is especially important to look at ways in which the development could help to reduce the overall consequences of flooding in the locality … through off-site works that benefit the area more generally.”

This proposal would significantly increase the number of people living in an area affected by very recent flooding and would increase the scale of any emergency evacuation considerably.  The FRA has not considered how this additional burden will be managed in the extreme flood event and has not suggested any off-site mitigations to reduce the overall consequence of flooding in the locality. We therefore object on the grounds that the additional burden on the emergency services in a flood event has not been given due consideration in the FRA.

A further objection is that the FRA fails to prove that the voluntary and free movement of people during a ‘design flood’ can be demonstrated.  Assessments of the adjacent Berkeley Homes WA/2014/0912 application site have shown that dry access/escape routes from the site across green fields are unsustainable in flood risk terms.  The FRA addendum (9 June 2015) for this site previously proposed an approximate 5km pedestrian diversion along unlit and unmade footpaths and public highways without footpaths.  This does not provide a safe nor appropriate route for people, especially for more vulnerable residents.

Evidence to support this is outlined in Appendix 1 of “Technical Review of Flood Risk Assessment (FRA) submitted by Berkeley Strategic Land Ltd WA/2014/0912 which demonstrates that every access route away from this adjacent development, using the Alfold Road, will be inaccessible by foot or car in a flood event like the one that occurred during 2013/14.

NPPF places significance with respect to land in the “Functional Floodplain” or Flood Zone 3b.  Figure 4.3 of Volume 3: Mapping of the WBC SFRA identified areas of Functional Floodplain within the borough. This figure shows parts of the development site are likely to be within the Functional Floodplain.

The extent of the Functional Floodplain is normally defined by the extent of flooding in the undefended 1 in 20 year (5% annual probability) event and the EA flood data indicates that parts of the site lie within the 1 in 20 year (5% annual probability) flood extent.  As the FRA has not delineated the extent of the Functional Floodplain at the site, we do not believe an appropriate nor up-to-date assessment of flood risk has been undertaken and object on these additional grounds.

The NPPF makes it very clear that the aim of the sequential test is to steer new development to areas with the lowest probability of flooding.  The Sequential Test provided by the applicant does not provide satisfactory justification as to why other suitable sites have been discounted.  We object on the grounds that the site fails the Sequential Test and the Exception Test cannot therefore be applied.  There is a site a far less risk of flooding for 120 dwellings currently at Appeal, the result of which will be available on 9 January 2017.  The council currently has a five-year housing supply and does not require housing on green fields at risk of flooding, on a flood plain, which will increase flooding elsewhere.

We also have concerns about the ability of new residents moving into the site to obtain meaningful flood risk insurance at an acceptable cost since the Association of British Insurers has stated that New Houses built after 1 January 2009 will not be covered by Flood Re; this is to avoid incentivising unwise building in flood risk areas.

The assessment of flood risk needs to demonstrate that the flood risks posed by the development can be managed, ae realistic, taking into account current climate change allowances, and are safe, the FRA fails to do this.”

Cranleigh Waters Partnership Meeting

Cranleigh Waters Partnership Meeting

Members of Cranleigh Civic Society met with representatives of the Environment Agency (EA) and Thames Water on Friday 16 December 2016 at Thames Water’s offices in Shalford.  Surrey Wildlife Trust (SWT) and Waverley Borough Council were invited but were unable to attend on the day.  However, Waverley have confirmed that they will be inviting all parties to a meeting in the New Year.

It was a productive meeting, with all parties keen to explore pollution issues in Cranleigh Waters and opportunities to improve the failing status of the river.

All attendees stressed the importance of the next stage of Waverley’s water cycle study and the news that Amec Group Ltd had been appointed to carry this out was welcomed.  This study is required as evidence for housing allocations in the Local Plan.  Although a water cycle scoping report was produced by Capita  (August 2016), it was recognised that the far more detailed stage two of the report  was required to identify constraints regarding  specific water supply and wastewater discharge, together with identifying upgrades required to the network and the accompanying timeline; taking into account costs, funding and available technology.

The EA confirmed that they had found Waverley’s Local Plan “unsound” based on the evidence presented to date.

Thames Water advised us that the trials to reduce phosphate levels in sewage effluent, should be available in Summer 2017.  It is not known yet whether the results of these trials are encouraging, or cost effective.  The situation remains that at present it is “technically infeasible” to reduce phosphate levels in discharged effluent to those required by the Water Framework Directive (WFD).

Cranleigh Civic Society is continuing its work with the EA and SWT on Cranleigh Waters with our Volunteer River Wardens.  We are currently requesting permission from landowners to access a longer stretch of the river so that we can carry out invertebrate studies and identify areas for possible restoration work, as well as the reason for continued low flow rates.

It was generally recognised that recent dredging work had severely impacted on flow rates and the ability of the river to maintain aquatic life.

Thames Water maintain that current expansion work at Elmbridge sewage treatment plant is to improve current resilience and not to accommodate growth.  They advised us that the plant would need to be expanded to deal with sewage from the significant housing estates granted in and around Cranleigh.  This would undoubtedly have a further impact on water quality.  However, it was not clear whether this upgrade work would involve a full planning application and Thames Water would not commit to carrying out an Odour Impact Assessment.

We stressed the need for this impact study in order to make sure that residents’ quality of life was not further impacted by odour nuisance.  Thames Water confirmed that complaints about odour from the sewage treatment works (SWT) had increased but they maintained that it was not clear that this corresponded to an increase in odour from the plant, or was due to the Cranleigh Society highlighting to residents that they could complain.  We would stress to residents that they should continue to report any odours from the STW in order that Thames Water have more accurate records.


Please continue to report odour nuisance to Thames Water email customerservices@thameswater.co.uk or 24-hour customer service team on 0800 316 9800 and to
Waverley Borough Council Environmental Health on 01483 523393.


Finally we discussed issues surrounding water supply and the recent spate of burst water mains. This will be discussed further at our next meeting.

In addition to the meeting in the New Year with Waverley, Thames Water is also helpfully arranging further meetings with their drainage and water supply departments.

Dunsfold Park Decision Called-in

Dunsfold Park Decision Called-in

Dunsfold Park WA/2015/2395  was granted permission by Waverley’s Joint Planning Committee (JPC) on 14 December in a recorded vote  of 10 Councillors in favour and 8 against.

Before the application went to committee there had been several reports of the application being called-in to the Secretary of State by Anne Milton MP, and the 11 Parish Councils, which form the Joint Parishes.

Subsequently on Thursday 15 December it was confirmed that a planning inspector had in fact been appointed to carry out an inquiry into the granted application. The inspector will report their recommendation to the Secretary of State who will then make the final decision on Dunsfold Park.


Calling-in Process

This is where an application goes to The Secretary of State (SoS) for Communities and Local Government, Sajid Javid MP, for his final consideration and determination.

Applications are called-in where planning issues of more than local importance are involved. This can include applications which:

  • Are of national significance.
  • Conflict with government policy.
  • Impact on long-term economic growth.
  • Have significant effects beyond their immediate locality.
  • Are controversial.
  • Raise significant architectural and urban design issues.
  • Involve national security or foreign governments

Where an application is called in, a planning inspector is appointed to hold an inquiry into the application and the Secretary of State takes the findings of this inquiry into account when they make their final decision.


The Dunsfold Debate

On the night of the JPC meeting, Surrey County Council Highways Department and the Environment Agency maintained their objections to the application on traffic impact and water quality.

The debate lasted over four hours.  Points in favour of the application included the total number of dwellings, including 30% affordable housing, which would meet a significant percentage of the borough’s housing need, as well as significant employment opportunities being provided on site (Dunsfold is already one of the biggest employment sites in the borough), a new primary school and a local bus service funded in perpetuity.  Cllr Foryszewski said:

 “This is a development we can be proud of, that can be exemplary, built for the future, to address how we live and work.”

Cllr Cockburn, also spoke in favour of the application saying that:

“We have been saying for years, use brownfield sites first, especially in Farnham and Cranleigh.”

However, councillors also voiced concerns about traffic. It was pointed out that significant impacts on the surrounding highways had led to the dismissal of the previous planning Appeal in 2009.  Furthermore, the robustness of traffic modelling  was brought into question and was said to be “more of an art than a science” .  The extent of objectors and the evidence they had submitted, including a professional transport study, should, it was noted, be taken seriously.  Although it was recognised that there would be considerable contributions from the applicants, amounting to a package of approximately £40M, which is proportionally far higher than those negotiated with other Cranleigh developers, the opportunity to deliver extensive road improvements, due to the limiting characteristics of the A281,  was questioned.

Cranleigh Civic Society would stress that we feel that these same characteristics should apply to the over 1,500 dwellings being proposed for our village too.

Cllr Mulliner (Haslemere East and Grayswood Ward) pointed out that this was the most significant site in Waverley and highly contentious,  having had over 5,000 objections submitted against it. He disagreed with officers on the point of prematurity with regard to the Local Plan, which he pointed out was at an advanced stage, having been agreed by full council two weeks previously, and was being submitted for examination by the inspector two days later on 16 December 2016 (the Local plan has 3,500 objections against it).

Dunsfold Park is listed as a Strategic Site in the Local Plan with a total of 2,600 dwellings proposed for the site.  Cllr  Mulliner expressed his concern that the application should not be determined until the Inspector had rigorously examined the Local Plan and agreed that the Dunsfold site should be included. Otherwise, he said, this could be predetermining the scale, position and phasing of 25% of Waverley’s entire housing allocation.  He went on to state that this was “clearest possible case of predetermination and pre-emption of the Inspector’s role”.

The Objectively Assessed Need (OAN) figure of 519 dwellings per year for the Waverley borough was also commented on.  This figure has already been challenged by the Neil MacDonald Report (September 2016).  The report concluded that the OAN figure should be reduced by approximately 120 dwellings per year. Over the lifetime of the local plan this could equate to a total decrease of 2,280 dwellings.

The MacDonald  concludes that:

The key issue emerging from this report is the significantly different picture painted by the most recent projections and population statistics from that set out in the SHMA. Whilst the SHMA suggests that the full objectively assessed need for housing in Waverley is 519 homes a year 2013-33, the analysis in this report indicates that an up to date estimate would lie in the range 400 +/- 30 homes a year.”

( SHMA = Strategic Housing Market Assessment.  The last assessment was carried out in September 2015 by GL Hearn and set the annual housing need for Waverley at 519 dwellings – see page 117)

GL Hearn, authors of the SHMA, in their response to the MacDonald report in November 2016  accepted the main point of the report.

5.13 In conclusion we recognise that if repeating this work today a different figure is likely to emerge, particularly as we would have a different starting point. This reflects the availability of data. However our approach is one that reflects the NPPF and PPG and remains a sound basis for planning.”

We now await the Inspector’s report to the SoS, which may take a couple of months to be issued.


You can watch the full Waverley meeting from 14 December 2016 here on YouTube.